Tuesday, December 26, 2017

Depot Avenue Area 36-inch Water Transmission Line Project

December 21, 2017 Update:
Garney Construction crews will continue site prep work and receiving construction materials next week (December 26-29). Garney also continues set up the equipment/storage yard and field office at 205 Patton Street. As previously noted, construction excavation will begin in early January on Blackstock Avenue area near the Western Avenue overpass.
KUB and its contractor would like to remind everyone to be mindful of the areas where crews have been working, as rough pavement and gravel may be present. Please exercise caution when travelling in these areas.
KUB will issue the next update for this project on January 5, 2018.